Flagging and Intermittent travel stoppages Water Street.
Flagging on 9th/Avon Street, Garrett Street, Levy Avenue, Graves Street, 6th Street SE, East South Street, Monticello Road and Old Avon.
Vehicular travel will be restricted 6th Street SE and Garrett Street. Sidewalk Closures on Garrett Street, 9th/Avon Street, Monticello Road, Graves Street, 6th Street SE and Old Avon Street. Crosswalk Closures on northern and eastern crosswalks at 9th/Avon/Garrett/Levy Intersection and eastern crosswalk at Garrett/6th Street SE intersection.
Intermittent pedestrian travel stoppages in pedestrian tunnel to/from the Downtown Mall via the Pavilion on Water Street.

posted in: Traffic Alert 0

The eastern bridge deck and girders have been removed across the old public parking lot and Old Avon Street.  Work is continuing over the railroad tracks and will progress to Water Street starting Wednesday, February 2nd.  Vehicular travel on Water Street will be restricted to one lane with flagging to accommodate 2 way travel.  Both vehicular and pedestrian travel on Water Street will be intermittently stopped for up to 15 minute intervals for certain work activities.  CAT buses will be given priority to maintain their schedules.

Public utility relocation continues – Garrett Street between 9th/Avon and 6th Street SE, 9th/Avon/Garrett/Levy intersection, Levy Avenue, East South Street, Graves Street between 9th/Avon and Monticello Road and Monticello Road from Graves Street to Old Avon.  Vehicular traffic will be flagged intermittently at these various locations in the daytime as connection points are unearthed, tested, disinfected and tied-in to activate the new waterline.  Work is expected to be complete next week.

A sanitary sewer pipe will begin relocation with flagging of vehicular traffic at the Garrett Street/6th Street SE intersection.   Vehicular travel will be restricted on two roads – 6th Street SE will be closed to northbound travel after Hinton Avenue before its connection with Garrett Street and Garrett Street will be closed to eastbound travel before 6th Street SE.   Work will progress to the east along Garrett Street with additional traffic impacts that will be announced in future traffic alerts.

Waterline work will continue from East South Street onto 6th Street SE Street.  Work will be completed with flagging of vehicular traffic in the daytime and no service interruptions are expected. 

To accommodate this utility work, segments of sidewalk and crosswalks will also be closed as work progresses down the alignment.  No street will have both sides of the sidewalk closed at the same time.  The eastern crosswalk at the Garrett Street/6th Street SE intersection will be closed with pedestrians directed to use the other three crosswalks.  The southern sidewalk along Garrett Street between 6th Street SE and 9th/Avon Street will be closed with the detour route being the northern sidewalk.  The northern sidewalk along Garrett Street between 6th Street SE and 9th/Avon Street will be closed with the detour route being the southern sidewalk.  The eastern sidewalk on 6th Street SE where it terminates at East South Street will be closed a few sidewalk segments earlier. The northern crosswalk at the 9th/Avon/Garrett/Levy intersection will be closed with pedestrians directed to use the other three crosswalks.  The eastern crosswalk across Levy Avenue at the 9th/Avon/Garrett/Levy intersection will be closed with pedestrians directed to use the other three crosswalks.  The eastern sidewalk on 9th/Avon Street between Levy Avenue and Graves Street will be closed with the detour route being the western sidewalk.  The eastern sidewalk on Monticello Road between Levy Avenue and Graves Street will be closed with the detour route being the western sidewalk.  The southern sidewalk along Graves Street between Monticello Road and Little Graves Street will be closed with the detour route being the northern sidewalk.

The southern sidewalk along Old Avon will be closed between Monticello Road and where it terminates near East South Street.

Monticello Road will be flagged intermittently between Graves Street and Old Avon Street as the crane removes full sections of the eastern bridge and a storm sewer line is installed.

Investigation continues for the footings of the existing pedestrian tunnel to/from the Downtown Mall via the Pavilion on Water Street.  Pedestrian travel through the tunnel will be intermittently stopped for 15 minute intervals. 

Pedestrian access will be maintained throughout the project area and access to private parcels will be accommodated.

Construction is being conducted by Caton Construction Group, Inc. for the City of Charlottesville’s Department of Public Works. The pedestrian pushbuttons at the 9th/Avon/Levy/Garrett intersection have been relocated to the large, wooden signal poles (NE, NW and SW corners) and an auxiliary wooden post with metal conduit (SE corner).

Work zone is posted at 25 MPH – please drive carefully with phones down.